INFRASTRUCTURE.REDEFINED.

Damaged roads rebuilt in about half the time, with 80–90% fewer truck loads.

Wirtgen WR Series
Soil stabilization · Cold recycling
German road rules
RStO 12/24 · FGSV 636 · FGSV 551
Fibre-reinforced asphalt
Tested by an accredited lab
BROOS PROJECT
— WHAT IS THE PROBLEM?

STRUCTURAL FAILURE, NOT SURFACE WEAR.

Inefficient logistics
A full rebuild means digging out the road and thousands of truck trips through town.
Patchwork instead of solutions
Recurring roadworks never address the root cause of the damage.
€53.7 bn backlog
Road maintenance backlog of German municipalities (KfW 2026). A third of the network has major defects (Difu).
Village road full of potholes
The repair cycleRepairs so far 0
01
Water gets in
02
Base softens
03
Pothole forms
04
It gets patched
↓ base still damaged
Rain seeps through fine cracks into the unbound base.
Wet material loses its load-bearing capacity and hollows form.
Traffic breaks the unsupported surface open.
The surface is fixed. The damaged base stays, and the cycle starts again.
PROBLEM · What Is the Problem?
02 / 25
BROOS PROJECT
— OVERVIEW

WHAT YOU WILL SEE TODAY

01SLIDES 04–08
Technological Excellence
—In-place soil stabilisation
—Fibre-reinforced asphalt
—Layer-by-layer comparison
—Where the method fits
02SLIDES 09–14
Digital Ecosystem
—Documented reference case
—CO₂ calculation per project
—Funding check per country
—Nexus: site & office connected
03SLIDES 15–18
Value for Everyone
—Mayor: political success
—Finance: lower cost per m²
—Engineers: rules & tests
—Citizens: immediate relief
OVERVIEW · What You Will See Today
03 / 25
BROOS PROJECT
— THE METHOD

TRANSFORMATION, NOT REPLACEMENT

01Existing soil
02Binder
03Wirtgen WR
04New load-bearing layer
up to 50 cmAsphalt · crackedBase · weakSubsoilNew load-bearing layerNew asphalt · after ≈ 24 hDirection of work →
RollerWirtgen WR recyclerBinder spreader
The damaged road and the weak base stay where they are. Cores and a lab test set the binder dose.
A spreader lays the cement-based binder at the calculated dose; a water tanker follows.
The Wirtgen WR mills the old asphalt and base up to 50 cm deep and mixes them with binder and water in one pass.
The roller compacts the mix into a new bound base layer. Asphalt can follow after about 24 hours.
No excavation · 80–90% less transport
The Wirtgen WR reuses the old road and soil on site — almost nothing goes to landfill.
Cement-based binder
Dose set by a lab suitability test; soil classified to DIN 18196.
Wirtgen WR 200 · WR 240 · WR 250
≈ half the construction time of a full rebuild. Asphalt after about 24 hours.
TECHNOLOGY · In-Place Method
04 / 25
BROOS PROJECT
— LAYER BY LAYER

SAME ROAD. TWO WAYS TO REBUILD IT.

Full rebuildDig out, truck away, rebuild
Existing ground
Asphalt · 26 cm
New gravel layer · 49 cm
↑ dug out and trucked away
Total 75 cm
Material moved by truck
72,000 t
Truck loads (25 t)
≈ 2,880
Construction time
5.5–6 months
In-place methodReuse what is already there
Existing ground
Asphalt · 26 cm
Old road + soil, bound in place · 26 cm
Total 52 cm
Material moved by truck
12,500 t
Truck loads (25 t)
≈ 500
Construction time
≈ 3 months
Source: published project report · district road, North Rhine-Westphalia · 3 km · load class Bk10 · 2023/24. Values differ by road; we calculate every project.
TECHNOLOGY · Layer by Layer
05 / 25
BROOS PROJECT
ASPHALT · FIBRE REINFORCEMENT

REINFORCED FROM WITHIN.

A high-strength synthetic fibre blend is mixed into the hot asphalt at the plant. It reinforces the whole layer in every direction and carries the tensile forces that crack ordinary asphalt.
≈ 50%
less rutting than the standard mix in lab tests
−25 °C
lab-tested cracking temperature of the mix
≈ 50%
less deformation under repeated load (lab)
Standard asphalt plant, standard paver. 100% recyclable.
01
Heavy traffic
02
Summer heat
03
Winter frost
Conventional
+50 °C−20 °C
Fibre-reinforced
+50 °C−20 °C
Trucks load the surface thousands of times a day.
Heat softens asphalt and the wheels press ruts into it. The reinforced layer keeps its shape.
Frost shrinks the layer until it cracks. In the reinforced layer the fibres bridge the crack.
TECHNOLOGY · Reinforced Asphalt
06 / 25
BROOS PROJECT
— BEFORE / AFTER

EXPERIENCE THE TRANSFORMATION

Recycler convoy on the freshly rebuilt road
Worn mountain road before renovation
BEFORE
AFTER
◀▶
Drag the slider — experience the Broos transformation interactively.
TECHNOLOGY · Before / After
07 / 25
BROOS PROJECT
— WHERE IT FITS

FOUR KINDS OF ROAD, ONE METHOD

01
Town & village streets
SHORT CLOSURES
Fewer trucks past front doors; residents get their street back sooner.
02
District & link roads
DOCUMENTED TO Bk10
The reference case is a district road in load class Bk10.
03
Farm & forest roads
FUNDING UP TO ≈ 53%
Rural-road programmes fund renewal, e.g. up to ≈ 53% in Schleswig-Holstein.
04
Cycle paths
≈ HALF THE TIME
Documented on a German cycle path: about half the time, 25% lower cost.
Not sure about your road? We assess it on site, free of charge.
TECHNOLOGY · Where It Fits
08 / 25
BROOS PROJECT
— DOCUMENTED REFERENCE CASE

A GERMAN DISTRICT ROAD, BOTH WAYS CALCULATED.

North Rhine-Westphalia · 3 km · ≈ 19,500 m² · load class Bk10 · 2023/24
−83%
material trucked
ItemFull rebuildIn-place methodDifference
Layer build-up49 cm gravel + 26 cm asphalt26 cm bound in place + 26 cm asphalt−23 cm
Material moved by truck72,000 t12,500 t−83%
Construction time5.5–6 months≈ 3 months≈ −50%
Cost per m²€150–160€102–107≈ −33%
CO₂1,000 t670 t−33%
PROOF · Reference Case
09 / 25
BROOS PROJECT
— CLIMATE

CO₂ SAVINGS YOU CAN DOCUMENT

DOCUMENTED
−83%
Material trucked
−33%
CO₂, documented case
30–60%
Typical CO₂ saving
GHG ProtocolPer-project calculationISO 14064-3 on request
CO₂ calculation per project
Diesel, transport and binder counted against a full rebuild of the same road.
Funding check
State programmesRural roadsAFIR · SalignyKÖYDES · IPARD III
Lower CO₂-price exposure
Fuel and cement carry a CO₂ price (Germany 2027: €55–65/t). Less diesel and transport lowers that hidden cost.
VALUE · CO₂ You Can Document
10 / 25
BROOS PROJECT
— FUNDING & INCENTIVES

FUNDING WE CHECK FOR YOU, BY COUNTRY

Germany
State road programmes (e.g. up to 50% in Baden-Württemberg); rural and farm roads via GAK, up to ≈ 53%.
State programmesGAK rural roadsSpecial fundKfW loans
Romania
Anghel Saligny for county and commune roads; AFIR DR-27 / DR-28 for agricultural and commune roads.
Türkiye
KÖYDES for village roads; IPARD III rural infrastructure (up to €3 m, 100% grant); İLBANK loans.
VALUE · Funding & Incentives
11 / 25
BROOS PROJECT
— BUILT IN-HOUSE · NEXUS

SITE AND OFFICE, CONNECTED.

Nexus is the software we built to connect work on site with the office. We improve it with the experience of every new project.

SITEOFFICE & ACCOUNTINGTimesheetsSite photos & statusMachines & GPSPlans & permitsStaff & qualificationsIncoming invoicesProject statusApproved hoursInvoicesDATEV exportRecords & documentationNEXUSBUILT BY BROOS
Built on our sites
Every module solves a problem our site and office teams had in daily work.
Your project in one place
Site photos, status, plans and permits are stored with the project, ready for handover.
Data in the EU
GDPR-compliant hosting in Frankfurt. Open to other contractors via nxs.digital.
PLATFORM · Nexus
12 / 25
BROOS PROJECT
— PROJECT PROCESS

FROM PLANNING TO COMPLETION

Click a step for details. Days are per road section.

01
Analysis
Before the start
02
Preparation
Day 1
03
Execution
Day 1–2
04
Completion
From day 2
05
Reporting
After 28 days
StartONE ROAD SECTIONAfter 28 days
Analysis
Analysis
Prep
Prep
Execution
Execution
Completion
Completion
Report
Report
AnalysisBefore the start
Cores along the road, utility survey and tar test. A lab suitability test sets the binder dose.
PreparationDay 1
A spreader lays the binder at the calculated dose; a water tanker follows.
ExecutionDay 1–2
The Wirtgen WR mills old road and soil up to 50 cm deep and mixes them with binder and water in one pass.
CompletionFrom day 2
Compaction, control cuts against cracks, then asphalt after about 24 hours with a fibre-reinforced surface.
ReportingAfter 28 days
Plate load tests, 28-day compressive strength and the CO₂ calculation, handed over as one file.
WHOLE PROJECT · DOCUMENTED 3 KM ROAD
In place ≈ 3 months
Full rebuild ≈ 6 months
VALUE · Project Process
13 / 25
BROOS PROJECT
— BEFORE WE START

WHAT WE CHECK FIRST, AND WHEN THE METHOD DOES NOT FIT

01
Pipes & cables
Utility survey and trial holes first: the rotor mixes down to 50 cm.
02
Tar in old asphalt
Every road is tested for tar (PAH) first. The rules differ by state.
03
Soil & binder dose
Cores along the road, soil class to DIN 18196, lab test sets the dose.
04
Slope, kerbs, level
Gradients up to 10%. New asphalt raises the road, so kerbs are checked.
05
Tests during work
Plate load tests (DIN 18134) and 28-day compressive strength.
06
Against cracks
Control cuts in the bound layer, fibre-reinforced asphalt on top.
If a road is not suitable, we say so and recommend the conventional rebuild.
PROOF · What We Check
14 / 25
BROOS PROJECT
— STRATEGIC ALIGNMENT

ONE DECISION. THREE WINS.

Select a stakeholder — every role benefits from the same decision.

BROOS PROJECT
01
Mayor
REPRESENTATION & CONSENSUS
Immediate political success citizens can see.
02
Finance Director
BUDGET CONTROL
Lower cost per m², funding checked, fewer repeat repairs.
03
Civil Eng. Office
ENGINEERING & EVIDENCE
Built to the German road rules, tested and documented.
VALUE · Strategic Alignment
15 / 25
BROOS PROJECT
— VALUE FOR THE MAYOR

VISIBLE LEADERSHIP.

01
Shorter closures
≈ HALF THE CONSTRUCTION TIME
Roads open again months earlier.
02
Less burden for residents
80–90% FEWER TRUCK LOADS
Less noise, dust and heavy traffic through town.
03
Documented climate benefit
30–60% LESS CO₂ · PER PROJECT
Figures you can use in your climate report.
Town square with a newly built road
Transformation citizens can see.
VALUE · Value for the Mayor
16 / 25
BROOS PROJECT
ESG dashboard on a desk
Costs you can check.
— VALUE FOR THE FINANCE DIRECTOR

LOWER COST.
FEWER REPEAT REPAIRS.

01
Lower cost per m²
25–35% CHEAPER
Documented: €102–107 instead of €150–160 per m².
02
Fewer repeat repairs
THE BASE IS FIXED
Not just the surface — the cause of the damage is removed.
03
Funding checked
STATE · RURAL · EU PROGRAMMES
We check every programme your road qualifies for.
VALUE · Value for the Finance Director
17 / 25
BROOS PROJECT
— VALUE FOR THE CIVIL ENGINEERING OFFICE

BUILT TO THE RULES. TENDER-READY. DOCUMENTED.

01
Built to the rules
RStO 12/24 · FGSV 636 · FGSV 551
Design input and lab suitability test included.
02
Tender-ready
PLANNED METHOD OR ALTERNATIVE BID
We supply tender wording and evidence.
03
Documented
PLANNING · SPECS · REPORTS · PROOF
Test results handed over as one file.
Engineer with a tablet next to a Wirtgen WR 240i
Proven method, documented results.
VALUE · Value for the Civil Engineering Office
18 / 25
BROOS PROJECT
— FOOTAGE FROM SITE

BROOS PROJECT IN ACTION.

1 pass
Milling and mixing in place
−83%
Material trucked, documented case
WR 250
Wirtgen machine
≈ 24 h
Until asphalt can follow
PROOF · Footage from Site
19 / 25
BROOS PROJECT
— MACHINES WE WORK WITH

THE RIGHT PRECISION FOR EVERY CHALLENGE

Wirtgen WR 200 soil stabilizer
SOIL STABILIZER
Wirtgen WR 200
Width 2.0 m
Depth 500 mm
540 hp
Wirtgen WR 250 road recycler
ROAD RECYCLER
Wirtgen WR 250
Width 2.5 m
571 hp
Deep recycling
Carbide milling drum
CARBIDE PRECISION
Milling Drum
200+ picks
mm-accurate
even depth
SANY STG motor grader
MOTOR GRADER
SANY STG
Blade 4.27 m
215 hp
GPS-guided
Site grader
TERRAIN GRADER
Site Grader
Shoulder work
Drainage
profiling
PROOF · Machines We Work With
20 / 25
BROOS PROJECT
— RULES & STANDARDS

BUILT TO THE GERMAN ROAD RULES.

01
RStO 12/24
Pavement design by load class, Bk0.3–Bk100
02
FGSV 636
Guideline for cold recycling in place (M KRC)
03
FGSV 551
Guideline for soil treatment with binders (M BmB)
04
ZTV E-StB 17
Earthworks contract terms, incl. soil treatment
05
TL / ZTV Beton-StB
Cement-bound layers, control cuts against cracks
06
DIN 18196 · DIN 18134
Soil classes · plate load test (Ev2)
07
TL / ZTV Asphalt-StB
Asphalt mixes for binder and surface course
08
RAP Stra
Tests by officially recognised road-testing labs
PROOF · Rules & Standards
21 / 25
BROOS PROJECT
— QUESTIONS WE HEAR MOST

SIX QUESTIONS, SIX SHORT ANSWERS

?Will the bound layer crack?
Cement-bound layers shrink. Control cuts set where, as the German rules require.
?What about frost?
The pavement is designed to RStO 12/24 for your frost zone.
?How long is the road closed?
On the documented road, about half as long as a full rebuild.
?What does it cost?
Documented: about a third less per m². We calculate your road first.
?Who else builds this way?
It is part of the FGSV guidelines; more than 20 projects in Baden-Württemberg alone.
?Can we put it out to tender?
Yes, as the planned method or as an alternative bid. We supply the wording.
PROOF · Questions
22 / 25
BROOS PROJECT
— ROAD CHECK

IS YOUR ROAD A CANDIDATE?

Tick what applies to the roads in your municipality.

Potholes come back after every repair.
Cracks run across the whole width of the road.
Ruts and deformations, especially where trucks drive.
The same stretch is repaired every year — and never lasts.
A full rebuild would mean months of closure and heavy truck traffic.
TWO OR MORE?
We assess your road on site — free of charge.
No obligation. You get a clear picture of the damage and your options.
0 of 5 apply
Request a free road check
NEXT STEPS · Road Check
23 / 25
BROOS PROJECT
— YOUR JOURNEY WITH BROOS

NEXT STEPS — START TODAY.

01
Free on-site consultation
Analysis of road problems & budget.
02
Cost comparison for your road
In place vs. full rebuild, with your road's data.
03
Technical concept & fixed-price offer
Lab suitability test, design to RStO 12/24.
04
Pilot project & live demonstration
The Broos difference on a test stretch.
BROOS PROJECT
Düsseldorf · HRB 104848
“Your infrastructure — our commitment.”
Scan to take this presentation with you.
Write to us
NEXT STEPS · Your Journey with Broos
24 / 25
BROOS PROJECT
— THE LEGACY OF RESPONSIBLE GOVERNANCE

A FOUNDATION FOR GENERATIONS.

“We don't just build roads. We build the trust of citizens in their administration.”
“We don't manage the damage of the past — we create lasting value for the future.”
What is the most pressing problem your municipality must solve today?
On-site consultationRequest a cost comparisonFunding documentation packageTechnical roundtable meeting